(  )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.
A、identify risks
B、monitor risks
C、impIement risks responses
D、plan risk management


相关试题

71题: (  )contributes to monitoring and data collection by defining security monitoring and date collection requirements.
A、information continuity management
B、information catalogue management
C、information security management
D、information distribution management
答案解析与讨论:www.wodishuixiang.com/st/4138811777.html

72题: () seek to perform root cause investigation as to what is leading identified trends.
A、 incident management
B、 prob lem management
C、change management
D、know ledge management
答案解析与讨论:www.wodishuixiang.com/st/4138916043.html

73题: the (  ) is a graph that shows the relationship between two variables.
A、histograms
B、flowcharts
C、matrix diagrams
D、Scatter diagrams
答案解析与讨论:www.wodishuixiang.com/st/4139014581.html

75题: work performance information is circulated through(  ) processes.
A、 planning
B、 change
C、 improvement
D、 communication
答案解析与讨论:www.wodishuixiang.com/st/4139218051.html